Phase 2 – site progress

Since our last update, Wates Construction, our main site contractor for Phase Two, have fully established themselves on site. They are now in their fourth month of the build programme and have been making positive progress. The concrete frame is complete, external cladding has started in earnest, over 100 bathrooms have been delivered to site and internal fit out of the apartments is about to commence in the next month. First completions in Phase 2 are scheduled for late 2019.